Zoning and permits

Zoning and permits in Bellevue, Washington

The City of Bellevue is divided into land use districts, also called zones, that spread land uses across the city. † This guide lists the districts, shows what the code says each is for and how to read the use chart, then walks through the permit steps, so you can check a site before you buy or lease it. It offers no permit service.

Last updated October 31, 2026

Photo: SounderBruce, Wikimedia Commons

Bellevue land use code: which version this page read

The online City of Bellevue Land Use Code is current through Ordinance 6839, passed March 4, 2025.† Some sections carry later notes. The parking section says it has been amended by Ordinance 6846, which is pending codification,† and by Ordinance 6851, also pending codification. †

This page read the code from captures current through the ordinance named above, plus the amendment notes noted here. A section may have changed since; check the City's current code before you rely on any line.

What is the zoning in Bellevue? The Land Use Code district list

The district list sits in Chapter 20.10, Land Use Districts,† where the code establishes each land use district in the City. † Our October 2026 research did not find every row of the list in a verified quote, so the table is not the whole list.

City of Bellevue Land Use Code 20.10.020, land use districts: district and designation †
DistrictDesignation
Professional OfficePO
Office †O
General Commercial †GC
Neighborhood Business †NB
Neighborhood Mixed Use †NMU
Community Business †CB
Light Industrial †LI
Eastgate Transit Oriented Development †EG-TOD
Medical Institution District †MI
Camp and Conference Center †CCC
BelRed Office/Residential †BR-OR

The list also includes "Office and Limited Business" (OLB)† and "Office and Limited Business 2" (OLB 2). †

Several areas have their own code part: Part 20.25A for Downtown,† Part 20.25D for BelRed,† Part 20.25R for the Mixed-Use Land Use Districts,† Part 20.25P for the Eastgate Transit Oriented Development Land Use District† and Part 20.25Q for the East Main Transit Oriented Development Land Use District. † Read both the district list and any area part that covers your site. Find the designation on the City's zoning map first. An area part can add rules the general chapter does not show.

What the code says each district is for

Here are three purpose statements in the code's own words, since the exact wording matters here. The Downtown line is one sentence from its section, not the whole statement.

General Commercial: "General Commercial is a mixed retail and commercial designation that provides for the location of a wide variety of business activities that provide goods and services to other businesses and the general public." †

Downtown, from section 20.25A.010: "It is to be developed as an aesthetically attractive area of intense use." †

BelRed: "BelRed is a major mixed use employment and residential area characterized by a transit-oriented, nodal development pattern, over time replacing the area’s original low intensity light industrial and commercial past." †

A purpose statement does not grant a use. If your project fits the stated purpose, say so in your application in the code's own words.

How to read the Bellevue use chart

Uses are listed in Chart 20.10.440, and its key has two marks: P for permitted use and C for conditional use.†† The office and commercial columns run across Professional Office, Office, "Office/Limited Business", General Commercial, Neighborhood Business and Community Business. † Find your use's row, read across to your district's column and note the mark. A blank cell is a question for the City before you sign, not after.

The City of Bellevue's own advice is the same: before you buy a property or lease a tenant space, find out what it is zoned and what uses are allowed. †

Bellevue code amendments under way

The council adopted the Wilburton TOD code amendments in June 2025 through Ordinance 6846.† The City Council agenda for Tuesday, May 5, 2026 listed council initiation of the Downtown Livability 2.0 Land Use Code Amendment.† A City meeting agenda for Wednesday, October 28, 2026 lists a public hearing on the BelRed Look Forward Land Use Code Amendment. † If your site is in an area with an amendment under way, read the draft as well as the adopted code. The rules at application can differ from the rules at closing.

Do I need a permit in Bellevue? The steps, in order

The City of Bellevue's Development Services handles land and building permits in one stop, and the process is completely paperless.†† Land use applications typically come before construction permit applications. †

  1. Preapplication conference. Some projects need preapplication review before a formal land use application.† The conference is free.† It happens at the schematic design phase, before you submit a formal application.† Materials go in online at least 21 days before the conference date.† Staff from the Building, Clearing & Grading, Land Use, Transportation, Utilities and Fire review groups may attend.† It is not meant to be a feasibility study. †
  2. Land use application and notice. Most land use applications require public notice. †
  3. Permit issued. The permit is issued to you electronically on your MyBuildingPermit dashboard. †
  4. Inspections. Schedule them online through MyBuildingPermit or by phone at 425-452-6875.† Scheduling all inspections and re-inspections is your responsibility. †
  5. Occupancy. Sign-off on the final building inspection is your authorization to occupy, unless a certificate of occupancy is required.† The City of Bellevue's building official issues certificates to the property owner before occupancy of all new commercial and multifamily buildings.† The list also includes commercial tenant improvements involving a change in use.† A temporary certificate, or TCO, is valid for 90 days. †

A permit has a clock: start the work within one year of issuance and finish it within three years.† The preapplication conference is also where you learn typical review and permitting schedules and fees, which helps you build realistic financing and construction schedules. † If your lease depends on a change of use, put the certificate of occupancy in the lease timeline. Ask the landlord who schedules inspections and who pays if one fails.

Bellevue Permit Center contacts, as the City lists them

In-person Permit Center services run Monday to Thursday, 10 a.m. to 3 p.m.† For permit questions, the City lists 425-452-4898 and permits@bellevuewa.gov.† You can also schedule one-on-one time with staff for general permitting questions.† Preapplication questions go to 425-452-4188 or landusereview@bellevuewa.gov. †

These are the City's own contacts, printed as the City lists them. This site has no permit desk and sends nothing to the City.

Sign permits and parking: where the rules are

Any sign erected, altered or relocated needs a sign permit.† The City of Bellevue's zoning page carves out temporary and exempt signs.† Design review rules for signs are in 22B.10.025.† The City Council approved the code amendments on June 9, 2026, with a delayed effective date of Feb. 1, 2027. †

Downtown parking counts are set in Part 20.25A. † Signage and parking often decide whether a retail or office tenant can open on time. Read both sets of rules for the exact address before you agree to a sign or parking clause.

Opening a restaurant: Public Health plan review

A restaurant needs plan review approval from Public Health - Seattle & King County before construction starts.† It also needs that approval and a pre-operational inspection before it starts operating.† Public Health says an initial review may take up to 8 to 10 weeks.† You apply through the Public Health Permit Center,† and the operating permit fee is separate from the plan review fee. † Confirm with Public Health that its review covers your site, and start health plan review alongside the City's building permit, not after it. A restaurant lease should give you time for both reviews before rent starts.

Questions about zoning and permits in Bellevue

How do I find out what a property is zoned in Bellevue?

Start with the City of Bellevue's zoning pages. The City says to find out what a property is zoned and what uses are allowed before you buy it or lease a tenant space there. †

Is a preapplication conference free in Bellevue?

Yes. The City of Bellevue calls the preapplication conference a free service. Materials must be submitted online at least 21 days before the conference date. ††

How do I schedule a building inspection in Bellevue?

Online through MyBuildingPermit or by phone at 425-452-6875, the City of Bellevue says. Scheduling all inspections and re-inspections is your responsibility. ††

Does a tenant improvement need a certificate of occupancy in Bellevue?

It can. The City of Bellevue says sign-off on your final building inspection authorizes you to occupy, unless a certificate of occupancy is required, and its list includes commercial tenant improvements involving a change in use. Ask the City whether your project needs one before you plan your move-in date. ††

How long is a Bellevue building permit good for?

Start the work within one year of issuance and finish it within three years of issuance, the City of Bellevue says. †

When does Bellevue's new sign code take effect?

February 1, 2027. The City of Bellevue says its updated sign code regulations take effect Feb. 1, 2027. †

Looking for an agent? See who is a commercial real estate agent in Bellevue, WA on the FAQ page.

Next step

Once you know the district and the steps, see what is already moving through review near your site.

See the development tracker